Phases of HDD jobs in Gas Pipe Project
HDD (Ciliwung Lama): Gas Pipe |
HDD or Horizontal Directional Drilling is a drilling lines
underground of Gas Pipe through the rivers, bridges or buildings that are
difficult to pass normally (mainline or opencut). Muara Karang-Muara Tawar of gas
pipe projects have made the job HDD namely: HDD Kali Blencong 1 KM, HDD
Ancol In, HDD Plumpang, HDD BKT, HDD Kali Begog, HDD PJB, HDD Pluit Laguna, HDD
landmark, HDD Gedong Panjang, HDD Pakin , and HDD Lodan.
Now being worked
on HDD Ancol Pasir Putih Regional and HDD Kodam (Ciliwung Lama) along 420
meters.
Reamer 18' HDD Kodam: Gas Pipe |
HDD Pasir Putih entrusted by KSO-HMP on subcont PT Titan,
while HDD Kodam (Ciliwung Lama) conducted by PT Line Inter Cikara leadership by
duo of brothers Heru Widayanto & Harry Widaryono. HDD Kodam (Ciliwung Lama)
to date has completed reamer 18 "this afternoon at 5 pm, after the
previous day finished penetration of 70 roots. Tomorrow will be implemented
reaming 24 "and continued reaming 32" before the pull back.
Here are the stages in the HDD work of Gas Pipe Project:
1. Mobilization of equipments & materials: Machine HDD (Vermeer
D130 x 150) for the tonnage of 65 tons of string gas pipeline, while VermeerMaxi (D 750 x 900) for the length of the land 1 KM to 2 KM. Other tools; Mixing
Pump, water tank car, roots, reamer, bentonite, etc.
2. Setting tools and equipments
3. Prepare a job description like jobs cabin operator,
rigger, freak man, man pump, joint roots man, helper and supervisor.
Crew & HSE Man (Gas Pipe) |
4. The operator and rigger set of paratrax and digit track
performance in accordance with the desired path.
5. Operator start of Vermeer assisted by rigger who install
root on the muzzle calibration.
6. One by one the roots get into the entry hole into the soil
up to the exit hole.
7. Installation of reamer 12 "or 18' at exit locations
to be drawn to the location entry, installation reamer 24 'and 32'
8. Process pullback after a few string of gas pipelines
installed launcher header gradually and continoue.
9. If the end of the string of gas pipelines have appeared at
the site of entry, then pull back work has been completed.
HDD Vermeer D130 x 150: Gas Pipe |
In the process of pull back often happens freak out or slurry
to the surface of the ground. This happens because of the structure, texture
and contour of soil is porous. In fact, often it does stagnation / gas pipeline
jammed or string can not be pulled or pushed. This incident could occur if the
lag time between the penetration process reamer 32' with pullback for too long,
so the bentonite mud stuck to the wall of the hole becomes hard and gripping
the pipe. Believe it or not, many also consider that stagnation occurs because
the pipe string ridden by spirits such as jin, genderuwo. Then, before the pull
back is usually held recitals in the mosque or sodaqoh by slaughtering a goat
and make tumpeng. Don't forget to read the others articles like Gas Pipeline in this blog.
No comments:
Post a Comment